Upon receipt of a Value Engineering Change Proposal (VECP), the Contracting Officer shall promptly forward it to the program office responsible for the contract, indicating:

(a) The date the VECP was received;

(b) The date by which the contractor must be informed of the government's acceptance or rejection of the VECP, unless additional time is required for evaluation;

(c) The date by which the Contracting Officer must know of the technical officer's decision in order to timely accept or reject the VECP;

(d) The need for information required to inform the contractor if the VECP is to be rejected or if additional time is needed to evaluate the VECP;

(e) The potential for awarding concurrent, future, or collateral savings to the contractor, if the VECP is accepted;

(f) That if the VECP is accepted, precise information will be needed with regard to the type of savings, and government costs, that can be expected from its acceptance;

(g) The need for a procurement request setting forth the specification changes to be used in a contract modification accepting the VECP in whole or in part; and

(h) The need for additional funds, if acceptance of the VECP will result in an increase in the cost of contract performance.


Tried the LawStack mobile app?

Join thousands and try LawStack mobile for FREE today.

  • Carry the law offline, wherever you go.
  • Download CFR, USC, rules, and state law to your mobile device.