48 CFR § 852.273-70
Late offers
November 17, 2020
As prescribed in 873.110(a), insert the following provision:
Late Offers (JAN 2003)
This provision replaces paragraph (f) of FAR provision 52.212-1. Offers or modifications of offers received after the time set forth in a request for quotations or request for proposals may be considered, at the discretion of the contracting officer, if determined to be in the best interest of the Government. Late bids submitted in response to an invitation for bid (IFB) will not be considered.