49 CFR § 192.745
Valve maintenance: Transmission lines
November 18, 2020
(a) Each transmission line valve that might be required during any emergency must be inspected and partially operated at intervals not exceeding 15 months, but at least once each calendar year.
(b) Each operator must take prompt remedial action to correct any valve found inoperable, unless the operator designates an alternative valve.
[Amdt. 192-43, 47 FR 46851, Oct. 21, 1982, as amended by Amdt. 192-93, 68 FR 53901, Sept. 15, 2003]