(a)
(1) adequate recipient staff organization with well-defined reporting relationships, statements of functional responsibilities, job descriptions, and job qualifications;
(2) a budget covering the project management organization, appropriate consultants, property acquisition, utility relocation, systems demonstration staff, audits, and miscellaneous payments the recipient may be prepared to justify;
(3) a construction schedule for the project;
(4) a document control procedure and recordkeeping system;
(5) a change order procedure that includes a documented, systematic approach to handling the construction change orders;
(6) organizational structures, management skills, and staffing levels required throughout the construction phase;
(7) quality control and quality assurance functions, procedures, and responsibilities for construction, system installation, and integration of system components;
(8) material testing policies and procedures;
(9) internal plan implementation and reporting requirements;
(10) criteria and procedures to be used for testing the operational system or its major components;
(11) periodic updates of the plan, especially related to project budget and project schedule, financing, and ridership estimates; and
(12) the recipient's commitment to submit periodically a project budget and project schedule to the Secretary.
[(b) Repealed. Pub. L. 114–94, div. A, title XI, §11316(p), Dec. 4, 2015, 129 Stat. 1679]
(c)
Amendments
2019—Pub. L. 115–420 renumbered section 24403 of this title as this section.
2015—Subsec. (b). Pub. L. 114–94 struck out subsec. (b) which related to secretarial oversight.
Effective Date of 2015 Amendment
Amendment by Pub. L. 114–94 effective Oct. 1, 2015, see section 1003 of Pub. L. 114–94, set out as a note under section 5313 of Title 5, Government Organization and Employees.