(a)
(1) the Administrator approves the application using criteria established by the Administrator;
(2) the design-build contract is in a form that is approved by the Administrator;
(3) the Administrator is satisfied that the contract will be executed pursuant to competitive procedures and contains a schematic design adequate for the Administrator to approve the grant;
(4) use of a design-build contract will be cost effective and expedite the project;
(5) the Administrator is satisfied that there will be no conflict of interest; and
(6) the Administrator is satisfied that the selection process will be as open, fair, and objective as the competitive bid system and that at least 3 or more bids will be submitted for each project under the selection process.
(b)
(c)
Effective Date
Section applicable only to fiscal years beginning after Sept. 30, 2003, except as otherwise specifically provided, see section 3 of Pub. L. 108–176, set out as an Effective Date of 2003 Amendment note under section 106 of this title.