Day1 | Event | Regulation |
---|---|---|
0 days | Request for review | 351.213(b) (Last day of the anniversary month) |
30 days | Publication of initiation | 351.221 (c)(1)(i) (End of month following the anniversary month) |
37 days | Application for an administrative protective order | 351.305(b)(3) |
60 days | Request to examine absorption of duties (AD) | 351.213(j) (30 days after date of publication of initiation) |
66 days2 | Notification of difficulty in responding to questionnaire | 351.301(c)(2)(iv) (14 days after date of receipt of initial questionnaire) |
66 days | Section A response | None |
85 days | Viability arguments | 351.301(d)(1) (40 days after date of transmittal of initial questionnaire) |
90 days3 | Sections B, C, D, E response | 351.301(c)(2)(iii) (At least 30 days after date of receipt of initial questionnaire) |
110 days | Company-specific cost allegations | 351.301(d)(2)(i)(B) (20 days after relevant section is filed) |
110 days | Major input cost allegations | 351.301(d)(3) (20 days after relevant section is filed) |
120 days | Withdrawal of request for review | 351.213(d)(1) (90 days after date of publication of initiation) |
130 days | Request for verification | 351.307(b)(1)(v) (100 days after date of publication of initiation) |
140 days | Submission of factual information | 351.301(b)(2) |
245 days (Can be extended) | Preliminary results of review | 351.213(h)(1) |
272 days4 | Submission of publicly available information to value factors (NME's) | 351.301(c)(3)(ii) (20 days after date of publication of preliminary results) |
282 days | Request for a hearing and/or closed hearing session | 351.310(c); 351.310(f) (30 days after date of publication of preliminary results) |
282 days | Submission of briefs | 351.309(c)(1)(ii) (30 days after date of publication of preliminary results) |
287 days | Submission of rebuttal briefs | 351.309(d)(1) (5 days after deadline for filing case briefs) |
289 days | Hearing; closed hearing session | 351.310(d)(1) (2 days after submission of rebuttal briefs) |
372 days (Can be extended) | Final results of review | 351.213(h)(1) (120 days after date of publication of preliminary results) |
382 days | Ministerial error comments | 351.224(c)(2) (5 days after release of disclosure documents) |
387 days | Replies to ministerial error comments | 351.224(c)(3) (5 days after filing of comments) |
1Indicates the number of days from the end of the anniversary month. Most of the deadlines shown here are approximate. The actual deadline in any particular segment of a proceeding may depend on the date of an earlier event or be established by the Secretary.
2Assumes that the Department sends out the questionnaire 45 days after the last day of the anniversary month and allows 7 days for receipt of the questionnaire from the date on which it was transmitted.
3Assumes that the Department sends out the questionnaire on day 45 and the response is due 45 days later.
4Assumes that the preliminary results are published 7 days after issuance (i.e., signature).