SUMMARY:

Pursuant to the authority delegated by the Commission's regulations, the Director of the Office of Energy Projects (OEP) computes and publishes the project cost and annual limits for natural gas pipelines blanket construction certificates for each calendar year.

DATES:

This final rule is effective March 3, 2021 and establishes cost limits applicable from January 1, 2021 through December 31, 2021.

FOR FURTHER INFORMATION CONTACT:

Richard W. Foley, Chief, Certificates Branch 1, Division of Pipeline Certificates, (202) 502-8955.

SUPPLEMENTARY INFORMATION:

Section 157.208(d) of the Commission's Regulations provides for project cost limits applicable to construction, acquisition, operation and miscellaneous rearrangement of facilities (Table I) authorized under the blanket certificate procedure (Order No. 234, 19 FERC ¶ 61,216). Section 157.215(a) specifies the calendar year dollar limit which may be expended on underground storage testing and development (Table II) authorized under the blanket certificate. Section 157.208(d) requires that the “limits specified in Tables I and II shall be adjusted each calendar year to reflect the 'GDP implicit price deflator' published by the Department of Commerce for the previous calendar year.”

Pursuant to § 375.308(x)(1) of the Commission's Regulations, the authority for the publication of such cost limits, as adjusted for inflation, is delegated to the Director of the Office of Energy Projects. The cost limits for calendar year 2021, as published in Table I of § 157.208(d) and Table II of § 157.215(a), are hereby issued.

Effective Date

This final rule is effective March 3, 2021. The provisions of 5 U.S.C. 804 regarding Congressional review of final rules does not apply to the final rule because the rule concerns agency procedure and practice and will not substantially affect the rights or obligations of non-agency parties. The final rule merely updates amounts published in the Code of Federal Regulations to reflect the Department of Commerce's latest annual determination of the Gross Domestic Product (GDP) implicit price deflator, a mathematical updating required by the Commission's existing regulations.

List of Subjects in 18 CFR Part 157

  • Administrative practice and procedure
  • Natural gas
  • Reporting and recordkeeping requirements

Issued: February 19, 2021.

Terry L. Turpin,

Director, Office of Energy Projects.

Accordingly, 18 CFR part 157 is amended as follows:

PART 157—APPLICATIONS FOR CERTIFICATES OF PUBLIC CONVENIENCE AND NECESSITY AND FOR ORDERS PERMITTING AND APPROVING ABANDONMENT UNDER SECTION 7 OF THE NATURAL GAS ACT

1. The authority citation for part 157 continues to read as follows:

Authority: 15 U.S.C. 717-717w, 3301-3432; 42 U.S.C. 7101-7352.

2. In § 157.208(d), Table I is amended by adding an entry for “2021” at the end of the table to read as follows:

§ 157.208
Construction, acquisition, operation, replacement, and miscellaneous rearrangement of facilities.
* * * * *

(d) * * *

Table I to Part 157

Year Limit
Auto. proj. cost limit (Col.1) Prior notice proj. cost limit (Col.2)
*   *   *   *   *
2021 $12,600,000 $35,600,000
* * * * *

3. In § 157.215(a)(5), Table II is amended by adding an entry for “2021” at the end of the table to read as follows:

§ 157.215
Underground storage testing and development.

(a) * * *

(5) * * *

Table II to Part 157

Year Limit
*   *   *   * *
2021 $6,800,000
* * * * *

[FR Doc. 2021-04096 Filed 3-2-21; 8:45 am]

BILLING CODE 6717-01-P


Tried the LawStack mobile app?

Join thousands and try LawStack mobile for FREE today.

  • Carry the law offline, wherever you go.
  • Download CFR, USC, rules, and state law to your mobile device.