(a) Any party found to be in violation of the regional standards may remediate by replacing the noncompliant unit at cost to the violator; the end user cannot be charged for any costs of remediation.
(1) If a violator is unable to replace all noncompliant installations, then the Department may, in its discretion, consider the remediation complete if the violator satisfactorily demonstrates to the Department that it attempted to replace all noncompliant installations.
(2) The Department will scrutinize any “failed” attempts at replacement to ensure that there was indeed a good faith effort to complete remediation of the noncompliant unit.
(b) The violator must provide to DOE the serial number of any outdoor unit and/or indoor unit installed not in compliance with the applicable regional standard as well as the serial number(s) of the replacement unit(s) to be checked by the Department against warranty and other replacement claims.
(c) If the remediation is approved by the Department, then DOE will issue a Notice of Remediation and the violation will not count towards a finding of “routine violator”.
[81 FR 45403, July 14, 2016]