(a)
(1) The estimated cost and schedule for the program established by the military department concerned, including—
(A) the dollar values estimated for the program acquisition unit cost, average procurement unit cost, and total life-cycle cost; and
(B) the planned dates for initial operational test and evaluation and initial operational capability.
(2) The independent estimated cost for the program established pursuant to section 2334(a)(6) of this title, and any independent estimated schedule for the program, including—
(A) the dollar values estimated for the program acquisition unit cost, average procurement unit cost, and total life-cycle cost; and
(B) the planned dates for initial operational test and evaluation and initial operational capability.
(3) A summary of any production, manufacturing, and fielding risks associated with the program.
(4) An assessment of the sufficiency of the developmental test and evaluation completed, including the use of automated data analytics or modeling and simulation tools and methodologies.
(b)
(c)
Amendments
2017—Subsec. (a)(4). Pub. L. 115–91 added par. (4).
Responsibility for Conducting Assessments; Guidance
For provisions designating officials responsible for conducting assessments and provisions requiring guidance for assessments under subsec. (a)(4) of this section, see section 838(a)(3), (4) of Pub. L. 115–91, set out as notes under section 2366b of this title.