(a) BOEM will review your submitted SAP, and additional information provided pursuant to §585.611, to determine if it contains the information necessary to conduct our technical and environmental reviews.
(1) We will notify you if we deem your proposed facility or combination of facilities to be complex or significant;
(2) We will notify you if your submitted SAP lacks any necessary information;
(b) BOEM will prepare NEPA analysis, as appropriate.
(c) As appropriate, we will coordinate and consult with relevant Federal and State agencies, executives of relevant local governments, and affected Indian Tribes and will provide to other Federal, State, and local agencies and affected Indian Tribes relevant nonproprietary data and information pertaining to your proposed activities.
(d) During the review process, we may request additional information if we determine that the information provided is not sufficient to complete the review and approval process. If you fail to provide the requested information, BOEM may disapprove your SAP.
(e) Upon completion of our technical and environmental reviews and other reviews required by Federal laws (e.g., CZMA), BOEM may approve, disapprove, or approve with modifications your SAP.
(1) If we approve your SAP, we will specify terms and conditions to be incorporated into your SAP. You must certify compliance with those terms and conditions required under §585.615(c); and
(2) If we disapprove your SAP, we will inform you of the reasons and allow you an opportunity to submit a revised plan making the necessary corrections, and may suspend the term of your lease, as appropriate, to allow this to occur.