(a) BOEM will review your submitted GAP, along with the information and certifications provided pursuant to §585.646, to determine if it contains all the required information necessary to conduct our technical and environmental reviews.
(1) We will notify you if we deem your proposed facility or combination of facilities to be complex or significant; and
(2) We will notify you if your submitted GAP lacks any necessary information.
(b) BOEM will prepare appropriate NEPA analysis.
(c) When appropriate, we will coordinate and consult with relevant State and Federal agencies and affected Indian Tribes and provide to other local, State, and Federal agencies and affected Indian Tribes relevant nonproprietary data and information pertaining to your proposed activities.
(d) During the review process, we may request additional information if we determine that the information provided is not sufficient to complete the review and approval process. If you fail to provide the requested information, BOEM may disapprove your GAP.
(e) Upon completion of our technical and environmental reviews and other reviews required by Federal law (e.g., CZMA), BOEM may approve, disapprove, or approve with modifications your GAP.
(1) If we approve your GAP, we will specify terms and conditions to be incorporated into your GAP. You must certify compliance with certain of those terms and conditions, as required under §585.653(c); and
(2) If we disapprove your GAP, we will inform you of the reasons and allow you an opportunity to resubmit a revised plan making the necessary corrections, and may suspend the term of your lease or grant, as appropriate, to allow this to occur.