(a) Except as provided in paragraphs (b) through (d) of this section, a recipient may not make any significant changes to a project for which a grant has been awarded without prior written approval from the VA National Grant and Per Diem Program Office. Significant changes include, but are not limited to, a change in the recipient, a change in the project site (including relocating, adding an annex, a branch, or other expansion), additions or deletions of activities, shifts of funds from one approved type of activity to another, and a change in the category of participants to be served.
(b) Recipients of grants involving both construction and non-construction projects must receive prior written approval from the VA National Grant and Per Diem Program Office for cumulative transfers among direct cost categories which exceed or are expected to exceed 10 percent of the current total approved budget.
(c) Recipients of grants for projects involving both construction and non-construction who are state or local governments must receive prior written approval from the VA National Grant and Per Diem Program Office for any budget revision which would transfer funds between non-construction and construction categories.
(d) Approval for changes is contingent upon the application ranking remaining high enough after the approved change to have been competitively selected for funding in the year the application was selected.
(e) Any changes to an approved program must be fully documented in the recipient's records.
(f) Recipients must inform the VA National Grant and Per Diem Program Office in writing of any key position and address changes in/of their organization within 30 days of the change, i.e., new executive director or chief financial officer, permanent change of address for corporate communications.
(The Office of Management and Budget has approved the information collection requirements in this section under control number 2900-0554)
(Authority: 38 U.S.C. 501, 2011, 2012, 2061, 2064)