(a) Criteria for determining whether a project is a new facility for the purpose of obtaining a production incentive include:

(1) The project requires a new site license or facility construction permit if it is on Federal lands;

(2) The project requires a new Commercial Use Permit;

(3) The project includes at least one new turbine-generator unit;

(4) The project involves a new sales contract;

(5) The project involves a new site or substantially larger footprint; and

(6) The project is not contiguous to an existing project.

(b) Generally, a new facility will not:

(1) Be permitted only with a Geothermal Drilling Permit;

(2) Be constructed entirely within the footprint of an existing facility; or

(3) Involve only well-field projects such as drilling new wells, increasing injection, and enhanced recovery projects.


Tried the LawStack mobile app?

Join thousands and try LawStack mobile for FREE today.

  • Carry the law offline, wherever you go.
  • Download CFR, USC, rules, and state law to your mobile device.