45 CFR § 1233.10
How does the Director make efforts to accommodate intergovernmental concerns?
April 14, 2021
CFR

(a) If a state process provides a state process recommendation to the Agency through its single point of contact, the Director either:

(1) Accepts the recommendation;

(2) Reaches a mutually agreeable solution with the state process; or

(3) Provides the single point of contact with a written explanation of the Agency's decision, in such form as the Director in his or her discretion deems appropriate. The Director may also supplement the written explanation by providing the explanation to the single point of contact by telephone, other telecommunication, or other means.

(b) In any explanation under paragraph (a)(3) of this section, the Director informs the single point of contact that:

(1) The Agency will not implement its decision for at least ten days after the single point of contact receives the explanation; or

(2) The Director has reviewed the decision and determined that, because of unusual circumstances, the waiting period of at least ten days is not feasible.

(c) For purpose of computing the waiting period under paragraph (b)(1) of this section, a single point of contact is presumed to have received written notification 5 days after the date of mailing of such notification.