10 U.S.C. § 3225
Verified against govinfo.gov as of June 20, 2026View official text on govinfo.gov ↗
The Director of Cost Assessment and Program Evaluation, and the Secretary of the military department concerned or the head of the Defense Agency concerned (as applicable), shall each—
- (1)issue guidance requiring a discussion of risk, the potential impacts of risk on program costs, and approaches to mitigate risk in cost estimates for major defense acquisition programs and major subprograms;
- (2)ensure that cost estimates are developed, to the extent practicable, based on historical actual cost information that is based on demonstrated contractor and Government performance and that such estimates provide a high degree of confidence that the program or subprogram can be completed without the need for significant adjustment to program budgets; and
- (3)include the information required in the guidance under paragraph (1)—
- (A)in any decision documentation approving a cost estimate within the baseline description or any other cost estimate for use at any event specified in section 3221(b)(6) of this title; and
- (B)in the next Selected Acquisition Report pursuant to section 4351 of this title in the case of a major defense acquisition program or major subprogram.