10 U.S.C. § 4253
Verified against govinfo.gov as of June 20, 2026View official text on govinfo.gov ↗
- (a)Not later than 15 days after granting Milestone C approval for a major defense acquisition program, the milestone decision authority for the program shall provide to the congressional defense committees and, in the case of intelligence or intelligence-related activities, the congressional intelligence committees a brief summary report that contains the following:
- (1)The estimated cost and schedule for the program established by the military department concerned, including—
- (2)The independent estimated cost for the program established pursuant to section 3221(b)(6) of this title, and any independent estimated schedule for the program, including—
- (3)A summary of any production, manufacturing, and fielding risks associated with the program.
- (4)An assessment of the sufficiency of the developmental test and evaluation completed, including the use of automated data analytics or modeling and simulation tools and methodologies.
- (b)At the request of any of the congressional defense committees or, in the case of intelligence or intelligence-related activities, the congressional intelligence committees, the milestone decision authority shall submit to the committee further information or underlying documentation for the information in a brief summary report submitted under subsection (a), including the independent cost and schedule estimates and the independent technical risk assessments referred to in that subsection.
- (c)In this section, the term “congressional intelligence committees” has the meaning given that term in section 437(c) of this title.