- (a)
- (1)In accordance with paragraph (2), the Director of the Missile Defense Agency shall establish and maintain an acquisition baseline for—
- (2)The Director shall establish an acquisition baseline required by paragraph (1) before the date on which the program element or major subprogram enters—
- (3)Except as provided by subsection (c), the Director may not adjust or revise an acquisition baseline established under this section.
- (b)Each acquisition baseline required by subsection (a) for a program element or major subprogram shall include the following:
- (1)A comprehensive schedule, including—
- (A)research and development milestones;
- (B)acquisition milestones, including design reviews and key decision points;
- (C)key test events, including ground, flight, and cybersecurity tests and ballistic missile defense system tests;
- (D)delivery and fielding schedules;
- (E)quantities of assets planned for acquisition and delivery in total and by fiscal year; and
- (F)planned contract award dates.
- (2)A detailed technical description of—
- (A)the capability to be developed, including hardware and software;
- (B)system requirements, including performance requirements;
- (C)how the proposed capability satisfies a capability requirement or performance attribute identified through—
- (D)key knowledge points that must be achieved to permit continuation of the program and to inform production and deployment decisions; and
- (E)how the Director plans to improve the capability over time.
- (3)A cost estimate, including—
- (A)a life-cycle cost estimate that separately identifies the costs regarding research and development, procurement, military construction, operations and sustainment, and disposal;
- (B)program acquisition unit costs for the program element;
- (C)average procurement unit costs and program acquisition costs for the program element;
- (D)an identification of when the document regarding the program joint cost analysis requirements description is scheduled to be approved; and
- (E)an explanation for why a program joint cost analysis requirements description has not been prepared and approved, and, if a program joint cost analysis requirements description is not applicable, the rationale for such inapplicability.
- (4)A test baseline summarizing the comprehensive test program for the program element or major subprogram outlined in the integrated master test plan.
- (1)A comprehensive schedule, including—
- (c)The Director may adjust or revise an acquisition baseline established under this section if the Director submits to the congressional defense committees notification of—
- (d)The Director shall ensure that each life-cycle cost estimate included in an acquisition baseline pursuant to subsection (b)(3)(A) includes—
- (1)all of the operations and sustainment costs for which the Director is responsible;
- (2)a description of the operations and sustainment functions and costs for which a military department is responsible;
- (3)the amount of operations and sustainment costs (dollar value and base year) for which the military department or other element of the Department of Defense is responsible; and
- (4)
- (A)a citation to the source (such as a joint cost estimate or one or more military department estimates) that captures the operations and sustainment costs for which a military department or other element of the Department of Defense is responsible;
- (B)the date the source was prepared; and
- (C)if and when the source was independently verified by the Office for Cost Assessment and Program Evaluation.