33 U.S.C. § 2347b
Verified against govinfo.gov as of June 20, 2026View official text on govinfo.gov ↗
- (a)
- (1)Not later than 90 days after the date of receipt of a complete application for a water storage project, the District Engineer shall develop and provide to the applicant a purpose and need statement that describes—
- (A)whether the District Engineer concurs with the assessment of the purpose of and need for the water storage project proposed by the applicant; and
- (B)in any case in which the District Engineer does not concur as described in subparagraph (A), an assessment by the District Engineer of the purpose of and need for the project.
- (2)No environmental impact statement or environmental assessment required under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) shall substantially commence with respect to a water storage project until the date on which the District Engineer provides to the applicant a purpose and need statement as required under paragraph (1).
- (1)Not later than 90 days after the date of receipt of a complete application for a water storage project, the District Engineer shall develop and provide to the applicant a purpose and need statement that describes—
- (b)A non-Federal interest may use the administrative appeals process described in part 331 of title 33, Code of Federal Regulations (or any succeeding regulation), in relation to a decision of the Secretary related to an application for a water storage project.