33 U.S.C. § 2735
Verified against govinfo.gov as of June 20, 2026View official text on govinfo.gov ↗
- (a)In addition to the requirements for response plans for vessels established by section 1321(j) of this title, a response plan for a tanker loading cargo at a facility permitted under the Trans-Alaska Pipeline Authorization Act (43 U.S.C. 1651 et seq.), and a response plan for such a facility, shall provide for—
- (1)prepositioned oil spill containment and removal equipment in communities and other strategic locations within the geographic boundaries of Prince William Sound, including escort vessels with skimming capability; barges to receive recovered oil; heavy duty sea boom, pumping, transferring, and lightering equipment; and other appropriate removal equipment for the protection of the environment, including fish hatcheries;
- (2)the establishment of an oil spill removal organization at appropriate locations in Prince William Sound, consisting of trained personnel in sufficient numbers to immediately remove, to the maximum extent practicable, a worst case discharge or a discharge of 200,000 barrels of oil, whichever is greater;
- (3)training in oil removal techniques for local residents and individuals engaged in the cultivation or production of fish or fish products in Prince William Sound;
- (4)practice exercises not less than 2 times per year which test the capacity of the equipment and personnel required under this paragraph; and
- (5)periodic testing and certification of equipment required under this paragraph, as required by the Secretary.
- (b)In this section—