33 U.S.C. § 701b–16 — Management of flood risk reduction projects
Verified against govinfo.gov as of June 20, 2026View official text on govinfo.gov ↗
- (a)In generalIf 2 or more flood control projects are located within the same geographic area, the Secretary shall, at the request of the non-Federal interests for the affected projects, consider those projects as a single program for budgetary or project management purposes, if the Secretary determines that doing so would not be incompatible with the authorized project purposes.
- (b)Cost share
- (1)In generalIf any work on a project to which subsection (a) applies is required solely because of impacts to that project from a navigation project, the cost of carrying out that work shall be shared in accordance with the cost-sharing requirements for the navigation project.
- (2)Use of amountsWork described in paragraph (1) may be carried out using amounts made available under subsection (a).