43 U.S.C. § 2402
Verified against govinfo.gov as of June 20, 2026View official text on govinfo.gov ↗
- (a)The Secretary, in cooperation with non-Federal project entities and consistent with this subchapter, may carry out a rural water supply program in Reclamation States to—
- (1)investigate and identify opportunities to ensure safe and adequate rural water supply projects for domestic, municipal, and industrial use in small communities and rural areas of the Reclamation States;
- (2)plan the design and construction, through the conduct of appraisal investigations and feasibility studies, of rural water supply projects in Reclamation States; and
- (3)oversee, as appropriate, the construction of rural water supply projects in Reclamation States that are recommended by the Secretary in a feasibility report developed pursuant to section 2405 of this title and subsequently authorized by Congress.
- (b)Any activity carried out under this subchapter shall be carried out in cooperation with a qualifying non-Federal project entity, consistent with this subchapter.
- (c)Not later than 1 year after December 22, 2006, the Secretary shall, consistent with this subchapter, develop and publish in the Federal Register criteria for—
- (d)The criteria developed under subsection (c) shall take into account such factors as whether—
- (e)The Secretary may include—
- (1)to the extent that connection provides a reliable water supply, a connection to pre-existing infrastructure (including impoundments and conveyance channels) as part of a rural water supply project; and
- (2)notwithstanding the limitation on population under section 2401(9)(A) of this title, a town or community with a population in excess of 50,000 inhabitants in an area served by a rural water supply project if, at the discretion of the Secretary, the town or community is considered to be a critical partner in the rural supply project.