50 U.S.C. § 3733
Verified against govinfo.gov as of June 20, 2026View official text on govinfo.gov ↗
- (a)The Secretary of Defense shall seek to obtain all the permits required to complete each phase of construction of a project under the Program in a state of the former Soviet Union before obligating more than 40 percent of the total costs of that phase of the project.
- (b)Except as provided in subsection (c), with respect to a new construction project to be carried out by the Program, not more than 40 percent of the total costs of the project may be obligated from Cooperative Threat Reduction funds for any fiscal year until the Secretary—
- (c)The limitation in subsection (b) on the obligation of funds for a construction project otherwise covered by such subsection shall not apply with respect to the obligation of funds for a particular project if the Secretary—
- (d)In this section, with respect to a project under the Program:
- (1)The term “new construction project” means a construction project for which no funds have been obligated or expended as of November 24, 2003.
- (2)The term “permit” means any local or national permit for development, general construction, environmental, land use, or other purposes that is required for purposes of major construction.