14 CFR §25.901
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)For the purpose of this part, the airplane powerplant installation includes each component that—
- (b)For each powerplant—
- (1)The installation must comply with—
- (2)The components of the installation must be constructed, arranged, and installed so as to ensure their continued safe operation between normal inspections or overhauls;
- (3)The installation must be accessible for necessary inspections and maintenance; and
- (4)The major components of the installation must be electrically bonded to the other parts of the airplane.
- (c)For each powerplant and auxiliary power unit installation, the applicant must comply with the requirements of § 25.1309, except that the effects of the following failures need not comply with § 25.1309(b)—
- (d)Each auxiliary power unit installation must meet the applicable provisions of this subpart.