- (a)An existing licensee whose license is subject to sections 14 and 15 of the Federal Power Act may apply for an exemption for the project.
- (b)An applicant for an exemption under paragraph (a) must meet the requirements of subpart K or subpart J of part 4 of this chapter, and §§ 16.5, 16.6, 16.7, 16.8, 16.9(b) (1), (2) (except the requirement to comply with §§ 4.41, 4.51, or 4.61 of this chapter), 16.9(c), 16.10(a), 16.10(b), and 16.10(d).
- (c)The Commission will process an application by an existing licensee for an exemption for the project in accordance with §§ 16.9(b)(3), 16.9(b)(4), and 16.9(d).
- (d)If a license application is filed in competition with an application for exemption filed by the existing licensee, the Commission will decide among the competing applications in accordance with the standards of § 16.13 and not in accordance with the provisions of § 4.37(d)(2) of this chapter.