18 CFR §16.2
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
For purposes of this part:
- (a)New license means a license, except an annual license, for a water power project that is issued under section 15(a) of the Federal Power Act after an original license expires.
- (b)New license application filing deadline, as provided in section 15(c)(1) of the Federal Power Act, is the date 24 months before the expiration of an existing license.
- (c)Nonpower license means a license for a nonpower project issued under section 15(b) of the Federal Power Act.
- (d)Subsequent license means a license for a water power project issued under Part I of the Federal Power Act after a minor or minor part license that is not subject to sections 14 and 15 of the Federal Power Act expires.