- (a)In determining whether the proposed hydroelectric project is best adapted to a comprehensive plan under section (10)(a)(1) of the Federal Power Act for improving or developing a waterway, the Commission will consider the extent to which the project is consistent with a comprehensive plan (where one exists) for improving, developing, or conserving a waterway or waterways affected by the project that is prepared by:
- (b)The Commission will treat as a state or Federal comprehensive plan a plan that: