StacksVerified U.S. regulatory reference

18 CFR §2.19

Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov
  1. (a)In determining whether the proposed hydroelectric project is best adapted to a comprehensive plan under section (10)(a)(1) of the Federal Power Act for improving or developing a waterway, the Commission will consider the extent to which the project is consistent with a comprehensive plan (where one exists) for improving, developing, or conserving a waterway or waterways affected by the project that is prepared by:
    1. (1)An agency established pursuant to Federal law that has the authority to prepare such a plan, or
    2. (2)A state agency, of the state in which the facility is or will be located, authorized to conduct such planning pursuant to state law.
  2. (b)The Commission will treat as a state or Federal comprehensive plan a plan that:
    1. (1)Is a comprehensive study of one or more of the beneficial uses of a waterway or waterways;
    2. (2)Includes a description of the standards applied, the data relied upon, and the methodology used in preparing the plan; and
    3. (3)Is filed with the Secretary of the Commission.