18 CFR §39.5
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)The Electric Reliability Organization shall file each Reliability Standard or modification to a Reliability Standard that it proposes to be made effective under this part with the Commission. The filing shall include a concise statement of the basis and purpose of the proposed Reliability Standard, either a summary of the Reliability Standard development proceedings conducted by the Electric Reliability Organization or a summary of the Reliability Standard development proceedings conducted by a Regional Entity together with a summary of the Reliability Standard review proceedings of the Electric Reliability Organization, and a demonstration that the proposed Reliability Standard is just, reasonable, not unduly discriminatory or preferential, and in the public interest.
- (b)The Electric Reliability Organization shall rebuttably presume that a proposal for a Reliability Standard or a modification to a Reliability Standard to be applicable on an Interconnection-wide basis is just, reasonable, not unduly discriminatory or preferential, and in the public interest, if such proposal is from a Regional Entity organized on an Interconnection-wide basis.
- (c)The Commission may approve by rule or order a proposed Reliability Standard or a proposed modification to a Reliability Standard if, after notice and opportunity for public hearing, it determines that the proposed Reliability Standard is just, reasonable, not unduly discriminatory or preferential, and in the public interest.
- (1)The Commission will give due weight to the technical expertise of the Electric Reliability Organization with respect to the content of a proposed Reliability Standard or a proposed modification to a Reliability Standard,
- (2)The Commission will give due weight to the technical expertise of a Regional Entity organized on an Interconnection-wide basis with respect to a proposed Reliability Standard or a proposed modification to a Reliability Standard to be applicable within that Interconnection, and
- (3)The Commission will not defer to the Electric Reliability Organization or a Regional Entity with respect to the effect of a proposed Reliability Standard or a proposed modification to a Reliability Standard on competition.
- (d)An approved Reliability Standard or modification to a Reliability Standard shall take effect as approved by the Commission.
- (e)The Commission will remand to the Electric Reliability Organization for further consideration a proposed Reliability Standard or modification to a Reliability Standard that the Commission disapproves in whole or in part.
- (f)The Commission may, upon its own motion or a complaint, order the Electric Reliability Organization to submit a proposed Reliability Standard or modification to a Reliability Standard that addresses a specific matter if the Commission considers such a new or modified Reliability Standard appropriate to carry out section 215 of the Federal Power Act.
- (g)The Commission, when remanding a Reliability Standard to the Electric Reliability Organization or ordering the Electric Reliability Organization to submit to the Commission a proposed Reliability Standard or proposed modification to a Reliability Standard that addresses a specific matter may order a deadline by which the Electric Reliability Organization must submit a proposed or modified Reliability Standard.