18 CFR §4.105
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)Exemption from provisions other than licensing. An application for exemption of a small hydroelectric power project from provisions of Part I of the Act other than the licensing requirement will be processed and considered as part of the related application for license or amendment of license.
- (b)
- (1)Consultation. The Commission will circulate a notice of application for exemption from licensing to interested agencies and Indian tribes at the time the applicant is notified that the application is accepted for filing.
- (2)Non-standard terms and conditions. In approving any application for exemption from licensing, the Commission may prescribe terms or conditions in addition to those set forth in § 4.106 in order to: