An application for license for transmission line only must contain the following information in the form specified.
  1. (a)Initial statement.
  2. (b)Required exhibits. The application must contain the following exhibits, as appropriate:
    1. (1)For any transmission line that, at the time the application is filed, is not constructed and is proposed to be connected to a licensed water power project with an installed generating capacity of more than 10 MW—Exhibits A, B, C, D, E, F, and G under § 4.41;
    2. (2)For any transmission line that, at the time the application is filed, is not constructed and is proposed to be connected to a licensed water power project with an installed generating capacity of 10 MW or less—Exhibits E, F, and G under § 4.61; and
    3. (3)For any transmission line that, at the time the application is filed, has been constructed and is proposed to be connected to any licensed water power project—Exhibits E, F, and G under § 4.61 of this chapter.