18 CFR §4.71
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
An application for license for transmission line only must contain the following information in the form specified.
- (a)Initial statement.
- (b)Required exhibits. The application must contain the following exhibits, as appropriate:
- (1)For any transmission line that, at the time the application is filed, is not constructed and is proposed to be connected to a licensed water power project with an installed generating capacity of more than 10 MW—Exhibits A, B, C, D, E, F, and G under § 4.41;
- (2)For any transmission line that, at the time the application is filed, is not constructed and is proposed to be connected to a licensed water power project with an installed generating capacity of 10 MW or less—Exhibits E, F, and G under § 4.61; and
- (3)For any transmission line that, at the time the application is filed, has been constructed and is proposed to be connected to any licensed water power project—Exhibits E, F, and G under § 4.61 of this chapter.