- (a)Notice. Within 14 days of the filing date of any application for a license developed pursuant to this part, the Commission will issue public notice of the tendering for filing of the application. The tendering notice will include a preliminary schedule for expeditious processing of the application, including dates for:
- (1)Issuance of the acceptance for filing and ready for environmental analysis notice provided for in § 5.22.
- (2)Filing of recommendations, preliminary terms and conditions, and fishway prescriptions;
- (3)Issuance of a draft environmental assessment or environmental impact statement, or an environmental assessment not preceded by a draft.
- (4)Filing of comments on the draft environmental assessment or environmental impact statement, as applicable;
- (5)Filing of modified recommendations, mandatory terms and conditions, and fishway prescriptions in response to a draft NEPA document or Environmental Analysis, if no draft NEPA document is issued;
- (6)Issuance of a final NEPA document, if any;
- (7)In the case of a new or subsequent license application, a deadline for submission of final amendments, if any, to the application; and
- (8)Readiness of the application for Commission decision.
- (b)Modifications to process plan and schedule. The tendering notice shall also include any known modifications to the schedules developed pursuant to § 5.8 for completion of consultation under section 7 of the Endangered Species Act and water quality certification under section 401 of the Clean Water Act.
- (c)Method of notice. The public notice provided for in paragraphs (a) and (b) of this Section will be given by:
- (1)Publishing notice in the Federal Register; and
- (2)Notifying appropriate Federal, state, and interstate resource agencies, state water quality and coastal zone management plan consistency certification agencies, Indian tribes, and non-governmental organizations, by electronic means if practical, otherwise by mail.
- (d)Resolution of pending information requests. Within 30 days of the filing date of any application for a license developed pursuant to this part, the Director of the Office of Energy Projects will issue an order resolving any requests for additional information-gathering or studies made in comments on the preliminary licensing proposal or draft license application.