- (a)General. The Federal agency will close out the award when it determines that all applicable administrative actions and all required work of the grant has been completed.
- (b)Reports. Within 90 days after the expiration or termination of the grant, the grantee must submit all financial, performance, and other reports required as a condition of the grant. Upon request by the grantee, Federal agencies may extend this timeframe. These may include but are not limited to:
- (1)Final performance or progress report.
- (2)Financial Status Report (SF-269) or Outlay Report and Request for Reimbursement for Construction Programs (SF-271) (as applicable).
- (3)Final request for payment (SF-270) (if applicable).
- (4)Invention disclosure (if applicable).
- (5)Federally-owned property report:
- (c)Cost adjustment. The Federal agency will, within 90 days after receipt of reports in paragraph (b) of this section, make upward or downward adjustments to the allowable costs.