29 CFR §1926.1432
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)Plan development. Before beginning a crane/derrick operation in which more than one crane/derrick will be supporting the load, the operation must be planned. The planning must meet the following requirements:
- (b)Plan implementation.
- (1)The multiple-crane/derrick lift must be directed by a person who meets the criteria for both a competent person and a qualified person, or by a competent person who is assisted by one or more qualified persons (lift director).
- (2)The lift director must review the plan in a meeting with all workers who will be involved with the operation.