40 CFR §35.2204
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)Minor changes in the project work that are consistent with the objectives of the project and within the scope of the grant agreement do not require the execution of a formal grant amendment before the grantee's implementation of the change. However, the amount of the funding provided by the grant agreement may only be increased by a formal grant amendment.
- (b)The grantee must receive from the Regional Administrator a formal grant amendment before implementing changes which:
- (1)Alter the project performance standards;
- (2)Alter the type of wastewater treatment provided by the project;
- (3)Significantly delay or accelerate the project schedule;
- (4)Substantially alter the facilities plan, design drawings and specifications, or the location, size, capacity, or quality of any major part of the project; or
- (5)Otherwise require a formal grant amendment under part 30 of this subchapter.
- (c)Notwithstanding paragraph (a) of this section, changes to Step 7 projects cannot increase the amount of EPA assistance established at the time of the grant amendment.