40 CFR §35.513
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)Notwithstanding the requirements of 2 CFR parts 200 and 1500, EPA may reimburse recipients for pre-award costs incurred from the beginning of the budget period established in the grant agreement if such costs would have been allowable if incurred after the award. Pre-award costs must be identified in the grant application EPA approves.
- (b)The applicant incurs pre-award costs at its own risk. EPA is under no obligation to reimburse such costs unless they are included in an approved grant application.