40 CFR §60.1295
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)Conduct initial stack tests for the pollutants listed in § 60.1285 within 60 days after your municipal waste combustion unit reaches the maximum load level at which it will operate, but no later than 180 days after its initial startup.
- (b)Conduct annual stack tests for the same pollutants after the initial stack test. Conduct each annual stack test no later than 13 months after the previous stack test.