- (a)If you are required to submit an application for a construction permit under 40 CFR part 51, subpart I, or 40 CFR part 52, you must submit five items by the date you submit your application.
- (1)Your draft materials separation plan, as specified in § 60.1065.
- (2)Your revised materials separation plan, as specified in § 60.1085(c).
- (3)Your notice of the initial public meeting for your draft materials separation plan, as specified in § 60.1070(b).
- (4)A transcript of the initial public meeting, as specified in § 60.1080(f).
- (5)The document that summarizes your responses to the public comments you received during the initial public comment period, as specified in § 60.1085(a).