40 CFR §61.09

Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov
  1. (a)The owner or operator of each stationary source which has an initial startup after the effective date of a standard shall furnish the Administrator with written notification as follows:
    1. (1)A notification of the anticipated date of initial startup of the source not more than 60 days nor less than 30 days before that date.
    2. (2)A notification of the actual date of initial startup of the source within 15 days after that date.
  2. (b)If any State or local agency requires a notice which contains all the information required in the notification in paragraph (a) of this section, sending the Administrator a copy of that notification will satisfy paragraph (a) of this section.