40 CFR §62.14560
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
For your control plan increment of progress, you must satisfy the two requirements specified in paragraphs (a) and (b) of this section.
- (a)Submit the final control plan that includes the six items described in paragraphs (a)(1) through (6) of this section.
- (1)A description of the devices for air pollution control and process changes that you will use to comply with the emission limitations and other requirements of this subpart.
- (2)The type(s) of waste to be burned.
- (3)The maximum design waste burning capacity.
- (4)The anticipated maximum charge rate.
- (5)If applicable, the petition for site-specific operating limits under § 62.14640.
- (6)A schedule that includes the date by which you will award the contracts to procure emission control equipment or related materials, initiate on-site construction, initiate on-site installation of emission control equipment, and/or incorporate process changes, and the date by which you will initiate on-site construction.
- (b)Maintain an on-site copy of the final control plan.