40 CFR §62.15215
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)Install, calibrate, maintain, and operate a continuous opacity monitoring system.
- (b)Install, evaluate, and operate each continuous opacity monitoring system according to § 60.13 of subpart A 40 CFR part 60.
- (c)Complete an initial evaluation of your continuous opacity monitoring system according to Performance Specification 1 in appendix B of 40 CFR part 60. Complete this evaluation by 180 days after your final compliance date.
- (d)Complete each annual evaluation of your continuous opacity monitoring system no more than 13 months after the previous evaluation.
- (e)Use tests conducted according to EPA Reference Method 9, as specified in § 62.15245, to determine compliance with the applicable opacity limit in tables 2 or 4 of this subpart. The data obtained from your continuous opacity monitoring system are not used to determine compliance with the opacity limit.