40 CFR §63.11463
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)This subpart applies to any existing or new affected source located at a secondary nonferrous metals processing facility.
- (b)The affected source includes all crushing and screening operations at a secondary zinc processing facility and all furnace melting operations located at any secondary nonferrous metals processing facilities.
- (c)An affected source is existing if you commenced construction or reconstruction of the affected source on or before September 20, 2007.
- (d)An affected source is new if you commenced construction or reconstruction of the affected source after September 20, 2007.