40 CFR §63.2832
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)You are an affected source subject to this subpart if you meet all of the criteria listed in paragraphs (a)(1) and (2) of this section:
- (1)You own or operate a vegetable oil production process that is a major source of HAP emissions or is collocated within a plant site with other sources that are individually or collectively a major source of HAP emissions.
- (i)A vegetable oil production process is defined in § 63.2872. In general, it is the collection of continuous process equipment and activities that produce crude vegetable oil and meal products by removing oil from oilseeds listed in Table 1 to § 63.2840 through direct contact with an organic solvent, such as a hexane isomer blend.
- (ii)A major source of HAP emissions is a plant site that emits or has the potential to emit any single HAP at a rate of 10 tons (9.07 megagrams) or more per year or any combination of HAP at a rate of 25 tons (22.68 megagrams) or more per year.
- (2)Your vegetable oil production process processes any combination of eight types of oilseeds listed in paragraphs (a)(2)(i) through (viii) of this section:
- (1)You own or operate a vegetable oil production process that is a major source of HAP emissions or is collocated within a plant site with other sources that are individually or collectively a major source of HAP emissions.
- (b)You are not subject to this subpart if your vegetable oil production process meets any of the criteria listed in paragraphs (b)(1) through (4) of this section:
- (1)It uses only mechanical extraction techniques that use no organic solvent to remove oil from a listed oilseed.
- (2)It uses only batch solvent extraction and batch desolventizing equipment.
- (3)It processes only agricultural products that are not listed oilseeds as defined in § 63.2872.
- (4)It functions only as a research and development facility and is not a major source.
- (c)As listed in § 63.1(c)(5) of the General Provisions, if your HAP emissions increase such that you become a major source, then you are subject to all of the requirements of this subpart.