40 CFR §63.7736
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)For each capture system subject to an operating limit in § 63.7690(b), you have demonstrated initial compliance if you have met the conditions in paragraphs (a)(1) and (2) of this section.
- (b)For each control device subject to an operating limit in § 63.7690(b), you have demonstrated initial compliance if you have certified in your notification of compliance status that:
- (c)For each bag leak detection system, you have demonstrated initial compliance if you have certified in your notification of compliance status that:
- (1)You have submitted the bag leak detection system monitoring information to the Administrator within the written O&M plan for approval according to the requirements of § 63.7710(b);
- (2)You will inspect, operate, and maintain each bag leak detection system according to the procedures in the plan; and
- (3)You will follow the corrective action procedures for bag leak detection system alarms according to the requirements in the plan.
- (d)For each pouring area and pouring station in a new or existing foundry, you have demonstrated initial compliance if you have certified in your notification of compliance status report that: