40 CFR §63.8995
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)If you have a new or reconstructed affected source, you must comply with this subpart according to paragraphs (a)(1) or (2) of this section.
- (1)If you start up your affected source before April 17, 2003, you must comply with the emission limitations and work practice standards in this subpart no later than April 17, 2003.
- (2)If you start up your affected source after April 17, 2003, you must comply with the emission limitations and work practice standards in this subpart upon startup of your affected source.
- (b)If you have an existing affected source, you must comply with the emission limitations and work practice standards no later than 3 years after April 17, 2003.
- (c)If you have an area source that increases its emissions or its potential to emit such that it becomes a major source of HAP, the provisions in paragraphs (c)(1) and (2) of this section apply.
- (1)Any portion of the existing facility that is a new affected source or a new reconstructed source must be in compliance with this subpart upon startup.
- (2)All other parts of the source must be in compliance with this subpart no later than the date 3 years after the area source becomes a major source.
- (d)You must meet the notification requirements in § 63.9045 according to the schedule in § 63.9045 and in subpart A of this part. Some of the notifications must be submitted before you are required to comply with the emission limitations in this subpart.