- (a)Dates of entry.
- (1)If an opt-in source provided monthly data under § 74.20, the opt-in source's opt-in permit may become effective at the beginning of a calendar quarter as of January 1, April 1, July 1, or October 1.
- (2)If an opt-in source provided annual data under § 74.20, the opt-in source's opt-in permit must become effective on January 1.
- (b)Prorating by Calendar Quarter. Where a combustion source's opt-in permit becomes effective on April 1, July 1, or October 1 of a given year, the Administrator will prorate the allowance allocation for that first year by the calendar quarters remaining in the year as follows: