StacksVerified U.S. regulatory reference

40 CFR Part 60, Table 1

Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov
Comply with these increments of progressBy these dates a
Increment 1—Submit final control plan(Dates to be specified in state plan)
Increment 2—Final compliance(Dates to be specified in state plan) b

a Site-specific schedules can be used at the discretion of the state.

b The date can be no later than 3 years after the effective date of state plan approval or March 21, 2016 for SSI units that commenced construction on or before October 14, 2010.