StacksVerified U.S. regulatory reference

40 CFR Part 63, Table 1

Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov
ReferenceApplies to subpart WComment
BLRWSRWSR equipment leak standard, and BLR equipment leak standard (40 CFR part 63, subpart H)
§ 63.1(a)(1)YesYes | Yes | Additional terms defined in § 63.522.
§ 63.1(a)(2)YesYes | Yes |
§ 63.1(a)(3)YesYes | Yes |
§ 63.1(a)(4)YesYes | Yes | Subpart W specifies applicability of each paragraph in subpart A to subpart W.
§ 63.1(a)(5)N/AN/A | N/A | Reserved.
§ 63.1(a)(6)YesYes | Yes |
§ 63.1(a)(7)YesYes | Yes |
§ 63.1(a)(8)NoNo | No | Discusses State programs.
§ 63.1(a)(9)N/AN/A | N/A | Reserved.
§ 63.1(a)(10)YesYes | Yes |
§ 63.1(a)(11)YesYes | Yes |
§ 63.1(a)(12)-(14)YesYes | Yes |
§ 63.1(b)(1)NoNo | No | § 63.521 of subpart W specifies applicability.
§ 63.1(b)(2)YesYes | Yes |
§ 63.1(b)(3)YesYes | Yes |
§ 63.1(c)(1)YesYes | Yes | Subpart W specifies applicability of each paragraph in subpart A to sources subject to subpart W.
§ 63.1(c)(2)NoNo | No | Area sources are not subject to subpart W.
§ 63.1(c)(3)N/AN/A | N/A | Reserved.
§ 63.1(c)(4)YesYes | Yes |
§ 63.1(c)(5)YesYes | No | Subpart H specifies applicable notification requirements.
§ 63.1(c)(6)YesYes | Yes |
§ 63.1(d)N/AN/A | N/A | Reserved.
§ 63.1(e)YesYes | Yes |
§ 63.2YesYes | Yes | Additional terms are defined in § 63.522 of subpart W; when overlap between subparts A and W occurs, subpart W takes precedence.
§ 63.3YesYes | No | Other units used in subpart W are defined in that subpart; units of measure are spelled out for subpart H.
§ 63.4(a)(1)-(3)YesYes | Yes |
§ 63.4(a)(4)N/AN/A | N/A | Reserved.
§ 63.4(a)(5)YesYes | Yes |
§ 63.4(b)YesYes | Yes |
§ 63.4(c)YesYes | Yes |
§ 63.5(a)YesYes | Yes | Except replace the terms “source” and “stationary source” in § 63.5(a)(1) of subpart A with “affected source”.
§ 63.5(b)(1)YesYes | Yes |
§ 63.5(b)(2)N/AN/A | N/A | Reserved.
§ 63.5(b)(3)YesYes | Yes |
§ 63.5(b)(4)YesYes | Yes |
§ 63.5(b)(5)YesYes | Yes |
§ 63.5(b)(6)YesYes | Yes |
§ 63.5(c)N/AN/A | N/A | Reserved.
§ 63.5(d)(1)(i)YesYes | Yes |
§ 63.5(d)(1)(ii)YesYes | Yes |
§ 63.5(d)(1)(iii)YesYes | Yes |
§ 63.5(d)(2)YesYes | Yes |
§ 63.5(d)(3)-(4)YesYes | Yes |
§ 63.5(e)YesYes | Yes |
§ 63.5(f)(1)YesYes | Yes | Except replace “source” in § 63.5(f)(1) of subpart A with “affected source”.
§ 63.5(f)(2)YesYes | Yes |
§ 63.6(a)YesYes | Yes |
§ 63.6(b)(1)-(2)NoNo | No | Subpart W specifies compliance dates.
§ 63.6(b)(3)-(4)YesYes | Yes |
§ 63.6(b)(5)| YesNo | Subpart H includes notification requirements.
§ 63.6(b)(6)N/AN/A | N/A | Reserved.
§ 63.6(b)(7)NoYes | No | Sources subject to subpart H must comply according to the schedule in § 63.520 of subpart W for new sources subject to subpart H.
§ 63.6(c)(1)-(2)YesYes | Yes | Except replace “source” in § 63.6(c)(1)-(2) of subpart A with “affected source”.
§ 63.6(c)(3)-(4)N/AN/A | N/A | Reserved.
§ 63.6(c)(5)YesYes | Yes |
§ 63.6(d)N/AN/A | N/A | Reserved.
§ 63.6(e)YesYes | Yes |
§ 63.6(e)(1)(i)Reserved. | |
§ 63.6(e)(1)(ii)See CommentYes, before July 15, 2027. No, beginning on and after July 15, 2027.
§ 63.6(e)(1)(iii)YesYes | Yes |
63.6(e)(2)N/AN/A | N/A | Reserved.
63.6(e)(3)See CommentYes, before July 15, 2027. No, beginning on and after July 15, 2027.
§ 63.6(f)(1)YesYes | Yes |
§ 63.6(f)(2)(i)-(ii)YesYes | Yes |
§ 63.6(f)(2)(iii)YesYes | Yes |
§ 63.6(f)(2)(iv)YesYes | Yes |
§ 63.6(f)(3)YesYes | Yes |
§ 63.6(g)YesYes | Yes | Affected sources have the opportunity to demonstrate other alternatives to the Administrator.
§ 63.6(h)NoNo | No | Subpart W does not contain any opacity or visible emissions standards.
§ 63.6(i)(1)YesYes | Yes |
§ 63.6(i)(2)YesYes | Yes | Except replace “source” in § 63.6(2) (i) and (ii) of subpart A with “affected source”.
§ 63.6(i)(3)YesYes | Yes |
§ 63.6(i)(4)(i)YesYes | Yes |
§ 63.6(i)(4)(ii)YesYes | Yes |
§ 63.6(i)(5)-(14)YesYes | Yes |
§ 63.6(i)(15)N/AN/A | N/A | Reserved.
§ 63.6(i)(16)YesYes | Yes |
§ 63.6(j)YesYes | Yes |
§ 63.7(a)(1)YesYes | No | Subpart H specifies required testing and compliance procedures.
§ 63.7(a)(2)(i)-(vi)YesYes | No | Subpart H specifies that test results must be submitted in the Notification of Compliance Status due 150 days after the compliance date.
§ 63.7(a)(2)(vii)-(viii)N/AN/A | N/A | Reserved.
§ 63.7(a)(2)(ix)YesYes | Yes |
§ 63.7(a)(3)YesYes | Yes |
§ 63.7(a)(4)YesYes | Yes |
§ 63.7(b)(1)YesYes | Yes |
§ 63.7(b)(2)YesYes | Yes |
§ 63.7(c)NoNo | No |
§ 63.7(d)YesYes | Yes | Except replace “source” in § 63.7(d) of subpart A with “affected source”.
§ 63.7(e)(1)Yes, before July 15, 2027. No, beginning on and after July 15, 2027.See § 63.525(l). Subpart W also contains test methods specific to BLR and WSR sources.
§ 63.7(e)(2)YesYes | Yes |
§ 63.7(e)(3)YesYes | No | Subpart H specifies test methods and procedures.
§ 63.7(f)YesYes | No | Subpart H specifies applicable methods and provides alternatives.
§ 63.7(g)(1)YesYes | No | Subpart H specifies performance test reporting. Additionally, this subpart specifies how and when the performance test results are reported for BLR and WSR.
§ 63.7(g)(2)N/AN/A | N/A | Reserved.
§ 63.7(g)(3)YesYes | Yes |
§ 63.7(h)(1)-(2)YesYes | Yes |
§ 63.7(h)(3)(i)YesYes | Yes |
§ 63.7(h)(3)(ii)-(iii)YesYes | Yes |
§ 63.7(h)(4)-(5)YesYes | Yes |
§ 63.8(a)(1)YesYes | Yes |
§ 63.8(a)(2)YesYes | Yes |
§ 63.8(a)(3)N/AN/A | N/A | Reserved.
§ 63.8(a)(4)YesYes | Yes |
§ 63.8(b)(1)YesYes | Yes |
§ 63.8(b)(2)YesYes | No | Subpart H specifies locations to conduct monitoring.
§ 63.8(b)(3)YesYes | Yes |
§ 63.8(c)(1)(i)Yes, before July 15, 2027. No, beginning on and after July 15, 2027.
§ 63.8(c)(1)(ii)YesYes | Yes |
§ 63.8(c)(1)(iii)Yes, before July 15, 2027. No, beginning on and after July 15, 2027.
§ 63.8(c)(2)-(3)YesYes | Yes |
§ 63.8(c)(4)-(8)NoNo | No | Subpart W specifies monitoring frequencies.
§ 63.8(d)NoNo | No |
§ 63.8(e)NoNo | No |
§ 63.8(f)(1)YesYes | Yes |
§ 63.8(f)(2)YesYes | Yes |
§ 63.8(f)(3)YesYes | Yes |
§ 63.8(f)(4)YesYes | Yes |
§ 63.8(f)(5)YesYes | Yes |
§ 63.8(f)(6)YesYes | No |
§ 63.8(g)YesYes | Yes |
§ 63.9(a)YesYes | Yes |
§ 63.9(b)(1)(i)-(ii)YesYes | Yes |
§ 63.9(b)(1)(iii)YesYes | Yes |
§ 63.9(b)(2)YesYes | Yes |
§ 63.9(b)(3)YesYes | Yes |
§ 63.9(b)(4)YesYes | Yes |
§ 63.9(b)(5)YesYes | Yes |
§ 63.9(c)YesYes | Yes |
§ 63.9(d)YesYes | Yes |
§ 63.9(e)NoNo | No |
§ 63.9(f)NoNo | No |
§ 63.9(g)NoNo | No |
§ 63.9(h)(1)-(3)YesYes | No | Separate Notification of Compliance Status requirements are specified for subpart H.
§ 63.9(h)(4)N/AN/A | N/A | Reserved.
§ 63.9(h)(5)-(6)YesYes | No | Subpart H specifies Notification of Compliance Status requirements.
§ 63.9(i)YesYes | Yes |
§ 63.9(j)YesYes | Yes |
§ 63.9(k)YesYes | Yes |
§ 63.10(a)YesYes | Yes |
§ 63.10(b)(1)YesYes | Yes |
§ 63.10(b)(2)NoNo | No | Subparts H and W specify recordkeeping requirements.
§ 63.10(b)(3)YesYes | Yes |
§ 63.10(c)(1)-(6)NoNo | No |
§ 63.10(c)(7)-(8)YesYes | Yes |
§ 63.10(c)(9)-(15)NoNo | No |
§ 63.10(d)(1)YesYes | No | Subpart H specifies performance test reporting requirements.
§ 63.10(d)(2)NoNo | No | This subpart and Subpart H specify performance test reporting requirements.
§ 63.10(d)(3)NoNo | No |
§ 63.10(d)(4)YesYes | Yes |
§ 63.10(d)(5)Yes, before July 15, 2027. No, beginning on and after July 15, 2027.
§ 63.10(e)(1)-(2)NoNo | No |
§ 63.10(e)(3)YesYes | No | Except that on and after July 15, 2027, the reports shall be submitted according to and in the format required by § 63.528(a).
§ 63.10(e)(4)NoNo | No |
§ 63.10(f)YesYes | Yes |
§ 63.11-63.15YesYes | Yes |

[60 FR 12676, Mar. 8, 1995, as amended at 85 FR 73891, Nov. 19, 2020; 89 FR 43274, May 16, 2024]

Editorial Note:At 89 FR 43274, May 16, 2024, table 1 to subpart W was amended in part by revising entry “§ 63.6(e)(1)(i)”. However, the amendment could not be incorporated due to an inaccurate amendatory instruction.

[60 FR 12676, Mar. 8, 1995, as amended at 89 FR 43274, May 16, 2024]