40 CFR Part 62, Table 4

Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov
Affected facilitiesIncrement 1Submit final control planIncrement 2Award contractsIncrement 3Begin on-site constructionIncrement 4Complete on-site constructionIncrement 5Final compliance
Affected facilities that commenced construction, modification, or reconstruction on or before June 26, 1987 (All pollutants)January 11, 199905/18/9911/16/9911/19/0012/19/00

a Table 4 or 5 of this subpart applies to MWC units subject to the Federal plan except those with site-specific compliance schedules shown in Table 6 of this subpart.

b As an alternative to this schedule, the owner or operator may close the affected facility by December 19, 2000, complete the retrofit while the affected facility is closed, and achieve final compliance upon restarting. See §§ 62.14108(c), 62.14108(d), and 62.14109(i) of this subpart.