42 CFR §137.364
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
A significant change in the original scope of work is:
- (a)A change that would result in a cost that exceeds the total of the project funds available and the Self-Governance Tribe's contingency funds; or