StacksVerified U.S. regulatory reference

42 CFR §137.364

Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov
A significant change in the original scope of work is:
  1. (a)A change that would result in a cost that exceeds the total of the project funds available and the Self-Governance Tribe's contingency funds; or
  2. (b)A material departure from the original scope of work, including substantial departure from timelines negotiated in the construction project agreement.