46 CFR §111.107-1
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)For the purpose of this subpart, an industrial system is a system that—
- (b)An industrial system that meets the applicable requirements of NFPA 70 (incorporated by reference; see § 110.10-1 of this subchapter) must meet only the following:
- (1)Part 110, subpart 110.25, of this chapter—Plan Submittal.
- (2)Subpart 111.01 of this part—General.
- (3)Subpart 111.05 of this part—Equipment Ground, Ground Detection, and Grounded Systems.
- (4)Sections 111.12-1(b) and 111.12-1(c)—Prime movers.
- (5)Sections 111.30-1, 111.30-5(a), and 111.30-19(a)—Switchgear.
- (6)Subpart 111.105 of this part—Hazardous Locations.
- (c)Cables that penetrate a watertight or fire boundary deck or bulkhead must—
- (1)Be installed in accordance with 46 CFR 111.60-5 and meet the flammability-test requirements of either IEEE 1202, IEC 60332-3-22:2018, or IEC 60332-3-21:2018, Category A or A F/R (all incorporated by reference; see § 110.10-1 of this subchapter); or
- (2)Be specialty cable installed in accordance with § 111.60-2.