46 CFR §154.703
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
Unless a cargo tank carrying methane (LNG) can withstand the pressure build up due to boil-off for 21 days, the pressure in the cargo tank must be maintained below the set pressure of the safety relief valve for at least 21 days by:
- (a)A refrigeration system that meets § 154.702;
- (b)A waste heat or catalytic furnace that burns boil-off gas, and:
- (c)Boilers, inert gas generators, and combustion engines in the main propelling machinery space that use boil-off gas as fuel; or
- (d)Equipment for services, other than those under paragraph (c) of this section, that use boil-off gas as fuel and that are located: